Boardman Pier Comes Into Focus

Jan. 28, 2015

Traverse City commissioners got their first look this week at the design for a proposed $8.7 million pier on the Boardman River mouth in downtown Traverse City – and will decide Monday whether to continue work on the project.

Consulting firm SmithGroupJJR was hired last summer with a $232,000 Great Lakes Fishery Trust grant to create schematic, preliminary and final engineering and construction designs for a proposed pier extending 500 feet into West Grand Traverse Bay. Commissioners must approve each phase of design work before progressing to the next. An early draft of the schematic design – created using resident input from multiple public workshops last fall – was released to commissioners Tuesday, with a final version to follow Monday.

The design calls for five phases of improvements that could be implemented over several years. Improvements surrounding the pier are designed to help connect the structure to the rest of downtown and offer increased public access to the site, according to City Planning and Engineering Assistant Missy Luick. Phases include:

1) Public pier, $5,360,000: Including pier, connection to Grandview Parkway, lower plaza, fish habitat structures, canopy structures, stormwater management, site amenities (lighting/landscaping/furnishings/signage)
2) Beach improvements, $660,000: Including public restrooms, fish cleaning station, canopy structure, sanitary sewer service, pump station, site amenities
3) Boardman River + Downtown, $1,150,000: Including boardwalk under Murchie Bridge, pedestrian bridge, Front Street plaza, connection to parking, bank stabilization, site amenities
4) East Connections, $630,000: Including improved TART connection, coastal wetland enhancement, boardwalk, connection to Grandview Parkway, site amenities
5) Clinch Marina Connection, $910,000: Including 12’ wide trail, three plazas/beach connections, stormwater management, site amenities

At $8.7 million, total cost estimates for the project are roughly 10 percent higher than an initially anticipated price tag of $8 million, according to SmithGroupJJR, who cited shallow water at the site and limited construction access for the rise in projections. 

SmithGroupJJR Senior Vice President Patrick Doher says the cost increases are “reasonable” given the overall scope of the project, noting they don’t affect the firm’s assessment of the project's feasibility. Dover adds that “the (next phase of) preliminary engineering…will allow a more refined and accurate cost to be developed.” City Manager Jered Ottenwess also says he doesn’t see anything in the design or cost estimates likely to prevent commissioners from proceeding with the remaining design phases, which are already paid for by the grant.

“It’s a large-dollar project, so whether it’s $8 million or $8.7 million, it’s still feasible and doable,” says Ottenwess.

The grant calls for final engineering and construction designs to be provided by SmithGroupJJR by June 1. If commissioners approve design work and decide to proceed, Luick says the city planning department would then commence fundraising for the project, which could potentially qualify for state and federal grants, coastal zone funding and Brown Bridge Trust Fund (BBTF) dollars.

Comment

Is There Light At The End Of The Tunnel For The Old Mission Wineries Lawsuit?

Read More >>

After The Flood: YMCA Leaders Talk Remediation Process, Reopening Plans

Read More >>

Northern Michigan’s Most Iconic Eats, 2026 Edition

Read More >>

The Uphill Battle Of Building A Wellness Hub In Traverse City

Read More >>

Major Downtown Properties Available, If The Price Is Right

Read More >>

Inaugural Great Lakes Child Safety Conference To Be Held Next Week

Read More >>

It's Time For The 20th Annual 40Under40

Read More >>

TCBN: Cool Properties, Cool Realtors, Top Sellers

Read More >>

Brown Bridge Road Closed Near Arbutus Road

Read More >>

Munson Medical Center Installs Comprehensive Security and Weapons Detection Systems

Read More >>

Sara Hardy Downtown Farmers Market Back This Weekend

Read More >>

After Opt-Outs From Grand Traverse County, BATA, And NMC, Is East Bay’s TIF Plan Still Alive?

Read More >>

Community Foundation Awards More Than $1.6 million to 156 Organizations

Read More >>

Tom’s Plans Ambitious “Market Village” Expansion of Fourteenth Street Site; More Retail, Restaurant News

Read More >>