Traverse City News and Events

City Approves Sidewalk Project, Delays Vote On Street Repairs

By Beth Milligan | April 17, 2018

Traverse City commissioners Monday approved a $915,000 contract with Elmer's to fix all city sidewalks with a rating of "poor" or "very poor" condition over the next two years. But commissioners for a second time declined to green light a $1.1 million contract with Elmer's for 2018 street repairs throughout the city, instead delaying the contract for a future vote over concerns about spending $300,000 to repave the north alley of Eighth Street.

Commissioners voted 5-1 to approve the sidewalk project, with Commissioner Brian McGillivary opposed and Commissioner Richard Lewis absent. The effort to upgrade over 15,000 feet of sidewalk in the worst condition in the city will take both the 2018 and 2019 construction seasons and is part of an overall planned $4.5 million project to to complete a decade’s worth of sidewalk gap, infill and repair work in an accelerated timeline of 3-4 years. Commissioners are expected to bond the $4.5 million for the project in the near future, though in order to get the project started immediately, the city will make a $915,000 inter-fund loan from its economic development fund to its capital projects fund to pay for the Elmer's contract. McGillivary expressed concerns about how the future bond would be paid off - suggesting the city seek a public millage or raise taxes to cover bond payments - and so voted against the project, citing a lack of answers on financing. However, other commissioners stated they were comfortable with City Manager Marty Colburn and City Treasurer Bill Twietmeyer's assessment that the city could afford the bond payments and was in a financially stable place to get the project rolling.

A second contract with Elmer's to make street repairs throughout the city proved more divisive Monday, with commissioners deciding to table the contract until a future meeting when all seven commissioners could be present to vote. The contract needs at least five affirmative votes from the commission to pass; at an April 2 meeting where it was first discussed, only six commissioners were present and voted 4-2 in support of the project, falling one vote shy of the needed majority. Even with the removal of a controversial project from the plan - the reconstruction of Parking Lot P on State Street, which is owned by a private developer but leased by the city - commissioners again failed to reach consensus on the pavement preservation project. Most contentious was the inclusion of a project to repave the north alley of Eighth Street for $300,000, a move meant to help accommodate traffic and provide access to businesses during the future reconstruction of the corridor. Some commissioners, including McGillivary and Michele Howard, said they either didn't think the alley reconstructon was necessary or preferred instead to take the funds and use them to temporarily repave Eighth Street. "I think a band-aid on Eighth Street is essential," Howard said.

Other commissioners, including Tim Werner and Brian Haas, said the alley repaving project was essential to the overall reconstruction plan for the corridor. However, both Werner and Haas said they were willing to have discussions during next month's budget planning about allocating funds for a skim coat of paint for Eighth Street, a project City Engineer Tim Lodge said could cost $220,000-$230,000. "I'm in favor of the alley and Eighth Street project overall, and I guess I'm not supportive of potentially derailing the larger project by shifting monies intended..for the alley for the street," said Werner. "Like Commissioner Haas, I was opposed to...a band-aid on Eighth Street for a number of years, but as (the reconstruction timeline) gets further out, I'm open to the possibility."

Lodge and Colburn both said the alley project was key to providing access to businesses during future reconstruction. "To me, it's an integral part of the project," Lodge said. "It's not a luxury that we're doing. It's something that we've committed to doing as part of the public involvement project...to try and avoid where you can't get to a business on the north side of Eighth Street." Lodge cautioned commissioners that the city had received a bid lower than anticipated for the alley repaving, and that if the project was delayed, it would have to be rebid and would likely be more expensive. Colburn also told commissioners the city was expected to have an answer in June on whether it would receive a significant state grant toward the Eighth Street reconstruction project, which would allow the city to give residents a clearer answer on when the actual road would be redone. Haas suggested commissioners "have an option" in the upcoming budget to do an overlay or skim coat on the road if funding fell through or the reconstruction timeline became "cloudy." Commissioners will revisit the pavement preservation contract at an upcoming meeting.

Comment

Folded Leaf Coming to Commongrounds, “Clean” Café Opening on Front Steet; More Restaurant/Retail News

Read More >>

Farmhouse Fire Shuts Down Hammond Road

Read More >>

The 2026 Bayshore Marathon Will Be An Olympic Trials Qualifying Event

Read More >>

Global Brand, Local Focus: Inside Interlochen's New Northern Michigan Opportunity Scholarship

Read More >>

Eater Names Traverse City Among 15 Top Food Destinations in 2026

Read More >>

Greenspire Addresses Future at Boardman Lake Campus

Read More >>

TCFD Makes Progress Toward Ambulance Expansion, But Staffing Remains Challenge

Read More >>

NMC Finalizes Boardman Lake Campus Sale

Read More >>

Sandwich Slingers: Behind The Scenes At A Downtown Institution

Read More >>

Traverse City Wineries Score National Awards

Read More >>

Road Commission Eyes Partnerships for Zimmerman Extension, More Road Projects

Read More >>

Staying the Course with Communities in Schools

Read More >>

The Summer Camp Shuffle: Your Guide To 2026 Sign-Up Season

Read More >>

City Street & Infrastructure Projects on Deck for 2026

Read More >>