Work Schedule, Closures Announced For Four Mile/Hammond Roundabout Construction

By Beth Milligan | June 17, 2021

Work on the construction of a new roundabout at the intersection of Four Mile and Hammond roads in East Bay Township starts this week. The Grand Traverse County Road Commission has released a work schedule for the project, which will take place in phases and is expected to heavily impact traffic through September in the area.

The work schedule is as follows:

Stage 1A – South Side Utilities – Approx. 2 weeks (June 16-June 29)
> Hammond westbound only
> Four Mile is completely closed

Stage 1B - North Half Roundabout Construction - Approx. 6 weeks (June 29-August 11)
> Hammond westbound only
> North portion of Four Mile open to westbound Hammond, and westbound Hammond to northbound Four Mile

Stage 2A - South Half, South and West Leg Roundabout Construction - Approx. 4 weeks (August 12-September 8)
> Hammond westbound only
> Four Mile North open to traffic (southbound from the north can only turn west)
> Four Mile South closed

> Stage 2B - South Half, South and West Leg Roundabout Construction - Approx. 3 weeks (September 9 - September 30)
> Hammond westbound only
> Four Mile North open to traffic (southbound from the north can only turn west)
> Four Mile South open to local traffic

Comment

Pavilions Charts New Course for Future

Read More >>

Teddy Bear Daycare and Preschool Announces Expansion at Church of the Living God

Read More >>

Your 2026 Winter Race Calendar

Read More >>

DDA Updates: 2026 Ballot Push for New TIF Plan, Downtown Events

Read More >>

Human Bake Ovens, Sea Serpents And More: Local Author Dives Into Slabtown History

Read More >>

New Audit Flags Financial Policy Shortcomings At Traverse City DDA From 2022 To 2024

Read More >>

County Approves Budget, Marijuana Funding Awards

Read More >>

Stone Hound, Two Sons Pizza Coming to Eighth Street; More Restaurant/Retail News

Read More >>

Remote Work Is Here To Stay, New Local Study Says

Read More >>

NMC To Sell Boardman Lake Campus To Grand Traverse Band Of Ottawa And Chippewa Indians

Read More >>

Grand Traverse Band Shares Plans For NMC Boardman Lake Campus

Read More >>

Marentette Contract, Complete Streets Policy, Density Changes, Gov Center Planning Approved

Read More >>

Welcoming the Winter Solstice

Read More >>

NMC Board Approves New Three-Year Strategic Plan

Read More >>