Traverse City News and Events

US-31 Work Not Expected To Be Complete Until August 28

By Beth Milligan | Aug. 5, 2020

Sewer line work on US-31 between Three Mile and Four Mile roads that was supposed to be completed by August 1 is now expected to take until August 28 to finish, project representatives told The Ticker Wednesday. Challenges with the project – including worse-than-expected underground conditions, rising water levels, and weather events including a large rainstorm that flooded the pipe with sand and sediment – are responsible for the schedule overrun. Because of a damages clause included in the construction agreement, contractors are facing a $500 daily penalty for every day they go beyond the scheduled August 1 completion date.

East Bay and Acme townships are funding the joint project to reconstruct a half mile of sewer line on US-31 between Three Mile and Four Mile roads.The deteriorating pipe is being reconstructed through a process called cured-in-place pipe (CIPP), a “trenchless” technology – meaning the old pipe doesn’t have to be dug up and replaced. Instead, a felt lining is inserted into the damaged pipe and exposed to hot water or steam that causes it to attach to the inner walls of the pipe – forming a new jointless, seamless inner pipe. This sealed “pipe within a pipe” keeps external water and tree and plant roots from infiltrating the system – factors that often contribute to sewer overflows. Insituform, considered an industry leader in installing CIPP, has been hired to complete the work. 

According to project representatives, Insituform is planning to finish the project and restore traffic to normal by Friday, August 28. As the project proceeds over the next few weeks, the contractor plans to restore areas they can and remove traffic control barricades and cones segment-by-segment in hopes of shortening the length of the lane closures along US-31. This restoration and barricade removal process is planned to start on the west end of the project and will proceed east, with the last area affected being the intersection of Hammond and Four Mile.

Challenges with the underground work have contributed to project delays, with crews uncertain of what they'd find when they start digging. Some parts of the infrastructure that workers are connecting to - originally thought to be in good condition - were in such bad shape they needed to be replaced. Rising water levels also hampered the project, requiring additional time for dewatering and managing flooded infrastructure. Weather was also a factor: In one instance, a large rainstorm came through and flooded the pipe cleaning operation, filling the pipe with sand and sediment and requiring it to be re-cleaned.

Insituform's contract includes a "liquidated damages" clause, meaning there is a penalty the contractor can be assessed in the event they don't complete work in the allotted contract time. The townships are expected to enforce that clause, resulting in a penalty of $500 per day assessed against the contractor for each day work goes beyond the contract schedule. The project schedule has the potential to be further delayed if there are any other unexpected underground surprises.

Earlier this week, East Bay Township Supervisor Beth Friend told The Ticker that it was "important to remember that as inconvenient as this project is, it is a proactive project (fully funded without raising any rates, taxes, or bonding) on a pressurized sewer line with a history of breaks and brittleness that required addressing." Project representatives have also said that while the CIPP project is incurring delays, the process is ultimately less disruptive, costly, and time-consuming than traditional methods of abandoning the old sewer line and installing a new line with an open-trench method.

Comment

Lakebed 2030 Conference Upcoming

Read More >>

More Than The Sum Of Its Parts: Cherry Capital Men's Chorus Hits 60 Years

Read More >>

Two-Way State Street Tweaks Coming

Read More >>

Northern Michigan Wins Big With Michigan Natural Resources Trust Fund Grants

Read More >>

TVC Charts Long-Range Plans

Read More >>

Health Department Warns Of Rabies-Positive Bat Found In Local Residence

Read More >>

Interlochen Announces 2026-27 Arts Academy Events Lineup

Read More >>

‘Nighttime Detour’ Announced For US-31 Next Week

Read More >>

Driver Killed in Peninsula Township Crash

Read More >>

TC Food & Wine, Dirt to Glass Kick Off This Week

Read More >>

City Manager Talks Building 'A Consortium Of Communities' To Advocate For New Tourism Tax

Read More >>

Child and Family Services Announces New Director

Read More >>

NMC Approves $13.5 Million Budget For Long-Gestating Student Services Hub

Read More >>

FishPass Enters Final Construction Stretch

Read More >>