Traverse City News and Events

US-31 Work Not Expected To Be Complete Until August 28

By Beth Milligan | Aug. 5, 2020

Sewer line work on US-31 between Three Mile and Four Mile roads that was supposed to be completed by August 1 is now expected to take until August 28 to finish, project representatives told The Ticker Wednesday. Challenges with the project – including worse-than-expected underground conditions, rising water levels, and weather events including a large rainstorm that flooded the pipe with sand and sediment – are responsible for the schedule overrun. Because of a damages clause included in the construction agreement, contractors are facing a $500 daily penalty for every day they go beyond the scheduled August 1 completion date.

East Bay and Acme townships are funding the joint project to reconstruct a half mile of sewer line on US-31 between Three Mile and Four Mile roads.The deteriorating pipe is being reconstructed through a process called cured-in-place pipe (CIPP), a “trenchless” technology – meaning the old pipe doesn’t have to be dug up and replaced. Instead, a felt lining is inserted into the damaged pipe and exposed to hot water or steam that causes it to attach to the inner walls of the pipe – forming a new jointless, seamless inner pipe. This sealed “pipe within a pipe” keeps external water and tree and plant roots from infiltrating the system – factors that often contribute to sewer overflows. Insituform, considered an industry leader in installing CIPP, has been hired to complete the work. 

According to project representatives, Insituform is planning to finish the project and restore traffic to normal by Friday, August 28. As the project proceeds over the next few weeks, the contractor plans to restore areas they can and remove traffic control barricades and cones segment-by-segment in hopes of shortening the length of the lane closures along US-31. This restoration and barricade removal process is planned to start on the west end of the project and will proceed east, with the last area affected being the intersection of Hammond and Four Mile.

Challenges with the underground work have contributed to project delays, with crews uncertain of what they'd find when they start digging. Some parts of the infrastructure that workers are connecting to - originally thought to be in good condition - were in such bad shape they needed to be replaced. Rising water levels also hampered the project, requiring additional time for dewatering and managing flooded infrastructure. Weather was also a factor: In one instance, a large rainstorm came through and flooded the pipe cleaning operation, filling the pipe with sand and sediment and requiring it to be re-cleaned.

Insituform's contract includes a "liquidated damages" clause, meaning there is a penalty the contractor can be assessed in the event they don't complete work in the allotted contract time. The townships are expected to enforce that clause, resulting in a penalty of $500 per day assessed against the contractor for each day work goes beyond the contract schedule. The project schedule has the potential to be further delayed if there are any other unexpected underground surprises.

Earlier this week, East Bay Township Supervisor Beth Friend told The Ticker that it was "important to remember that as inconvenient as this project is, it is a proactive project (fully funded without raising any rates, taxes, or bonding) on a pressurized sewer line with a history of breaks and brittleness that required addressing." Project representatives have also said that while the CIPP project is incurring delays, the process is ultimately less disruptive, costly, and time-consuming than traditional methods of abandoning the old sewer line and installing a new line with an open-trench method.

Comment

Birdy Flight: The Story Of Traverse City's Newest Low-Alcohol Wine

Read More >>

DDA Could Send New TIF Plan to November Ballot

Read More >>

County Commissioners Agree to Meet with Twin Lakes Plaintiffs

Read More >>

Housing North Names New Executive Director

Read More >>

Dojo Sushi & Bonobo Winery Target July Opening for New Venture; More Restaurant, Retail News

Read More >>

Sheriff's Office Issues Statement on Guilty Verdict in Cold Case Murder

Read More >>

GT County Trail Millage Proposed

Read More >>

Abra Berens & Erik Hall to Launch Teaching Kitchen in TC

Read More >>

Proposed 80-Home Garfield Development Runs Into Road, Tree-Clearing Concerns

Read More >>

State Approval Sought for Kelley Park Boat Launch

Read More >>

Water 101 with The Watershed Center

Read More >>

'Spotty' Cherry Crop Looms, But Grapes Look Good

Read More >>

Munson Nurses Approve New Contract

Read More >>

Workforce Apartments Proposed Near Filling Station

Read More >>